The Railway Station – Part 1

In the  history of the village school,  I mentioned in Part 6 that  pupils were set the  challenge of measuring the distance from the school gate to the railway station:  1 mile and 8 chains, according to the school diary!   This prompted one   recent newcomer to Weston   to comment that they  didn’t know the village ever had a railway station.  As  it closed some  60 years ago,   only very long term residents will   have any first hand memories of this service, which  has    prompted me to   look back  at another facility  now lost to us.

After the crossroads with Buckle Street, the B4035   Bretforton road  snakes  its way   up and  over  the old railway line. The track   is long gone, as is  the station, with the site now occupied by CRH Plant.   But what  brought   trains to Weston?

The  19th century saw a  period of railway ‘mania’. In 1830 there were just 125 miles of track, but by 1871, this had increased to  over 13,000 miles.   One reason for this vast expansion was the lack of Government regulation or intervention.  Anyone  with sufficient financial means  (or  the capacity  to  borrow funds)  could form a railway company, raise capital and put forward an application for a Railway Bill  to Parliament  which, if passed, would  enable    land along the  proposed route to be compulsorily purchased and work commenced.

There was   no grand  master plan, with individual routes being developed by  companies formed  for  a  specific purpose.   One of these was the Birmingham & Gloucester Railway Company.  Running via Cheltenham and Bromsgrove,  this  service was opened in sections and  completed in August 1841.

Closer to  Weston,  the Oxford, Worcester and Wolverhampton Railway Company  constructed their line from Wolvercote   (near Oxford)  to Evesham, and  began running  trains in June 1853.    Local stations  were Mickleton (subsequently renamed Chipping Campden)  and Honeybourne.  This is essentially   the main line still running today, although Camden station closed in 1966.

A number of schemes to serve the Vale of Evesham were floated, but  it was not until 1902 that work  began to connect Cheltenham and Honeybourne. However, before we look at the history of that line, upon which Weston was one of the stations, I  am going on a slight detour and     take a closer look   at  construction of the  mile long tunnel  on the line between Moreton-in-Marsh and Honeybourne.  Work  started in 1846, but progress by the contractor was slow and resulted in the Railway Board eventually ordering their Chief Engineer, Isambard Kingdom Brunel, to take over the project himself.

This proved easier said than done!

Next month: The battle for Campden Tunnel

(Published in The Messenger June 2021)

The Railway Station – Part 2

Where was the last battle  on UK soil fought between two private armies?  For a likely candidate  we need to look no further than the construction of the  mile long tunnel on the railway  line   between Moreton and Honeybourne.

Work started in 1846, but was beset with problems from the beginning. The scheme  was suspended   in  1848 and  resumed again  in 1851 but  in July of that  year the Railway Board ordered their Chief Engineer, Isambard Kingdom Brunel, to dismiss the tunnel contractor, take possession of the site   and plant,  and  hand them over to Messrs Peto & Betts,   the firm who were   building the  rest of the line.   Not surprisingly, Mr  Robert Marchant, the tunnel contractor, took exception to this and refused to leave.  He  kept his team of navvies on guard, and   drove  off all   attempts  by Peto & Betts   to take possession.

After a number of   skirmishes,    Brunel  decided to settle  the matter  himself.   Arriving  on Friday  July 20th  1851, with a considerable body of men,  he discovered that Marchant  had been tipped off, and had  persuaded local magistrates to attend.   Brunel retreated but  returned the next day only to find the magistrates  still there  and now  joined  by a large force of  policemen.  As a fight between the two opposing forces seemed inevitable the magistrates read the Riot Act.   Brunel and his   navvies withdrew again.

Whilst   giving the impression of having abandoned  all hope of taking over the tunnel, Brunel  secretly  organised   reinforcements  and  under cover of  darkness on the next night,    gangs of navvies   awoke village after village as they   marched through, en route to the tunnel.  Reports vary,  but it is likely that   some  2,000 men  assembled   under Brunel’s command.

In the face of this show of strength, Marchant retreated,  but  soon returned with  three dozen policemen,  some privates  of the Gloucestershire Artillery, and two magistrates, who again read the Riot Act.  In spite of the draconian penalties of this legislation (refusal to disperse was an offence carrying the death penalty) the rival forces continued to   confront  each other, armed with spades, picks, clubs and a few pistols.  Scattered fighting  broke out  throughout  the day,  until Marchant finally accepted  that he was outnumbered.    He  went to Brunel  and they agreed to refer the whole  dispute to arbitration.  Peace was concluded  just before the  troops,  called in to help the police,  arrived from Coventry.

Thus ended the  ‘Battle for Campden Tunnel’  with the  project being completed eventually in the spring of 1852.

Next month: The start of the line from  Cheltenham to Honeybourne .

(Published in The Messenger  July 2021)

 

The  Railway Station – Part 3

The Bill authorising  construction of the line between Cheltenham and Honeybourne, upon which Weston was one of the stations,  was  presented to Parliament in November 1898  and received Royal Assent in August 1899.

The Great Western Railway Board awarded  four separate contracts  for the work, all to  Messrs Walter Scott & Middleton, with a total value of  £340,000 (equivalent to about £45million today).  Work started on the section from Honeybourne to Winchcombe,   to avoid adding to the  disruption being suffered in Cheltenham from  the installation of its own tramway system.

First,  the  centre line of the  route was marked out and   the land (which had been  compulsorily  purchased) then fenced off and a temporary track   laid  for use by steam navvies –  excavators with large  buckets on their booms that could handle one ton of  earth at a time.   Tip  wagons, filled by either the steam navvies or men, were   pulled by steam locomotives ( or sometimes horses)   from cuttings  to points on the line where embankments required building up.

It would be remiss of me not to mention the navvies, named after the ‘navigators’ who built the first navigation canals in the 18th century.   Although the introduction of the steam navvies  reduced manpower requirements,     there was still a need for  these tough individuals.   Well paid by the standards of the day, the work was hard and (before the days of Health and Safety) often very dangerous, as we will discover next month. While some found accommodation in  local villages, many  had to put up with primitive living conditions in temporary camps  set up along the course of the line.  Sleeping sixteen men to each hut, they would each  pay about 2 shillings (10p) per week to a hut keeper  for board and  cooking their food.  The hut  keeper in turn hired the hut from the contractor.

Navvies  also  became renowned for their drunkenness  and unruly behaviour.   As we  saw in the history of the village school,   Canon Bourne took exception to   their  presence at the annual Dover’s Games.  This prompted him to   have the Games closed down,  leading indirectly  to the  building  of the village school.   Although   Canon Bourne had achieved his objective   some years before,   we can only guess at  the Reverends’  reaction to the hoards of navvies marching through local villages  at the dead of night en route to the Battle of Campden Tunnel ( see Part 2).

My main source for the foregoing, and indeed the bulk of the remaining chapters on the railway station,  has been the ‘Illustrated History  of the Stratford-upon-Avon to Cheltenham Railway’  by the late Audie Baker.

Next month; Tragedy at Toddington Viaduct.

(Published in The Messenger August 2012)

 

The Railway Station – Part 4

 The   planner for the Cheltenham to  Honeybourne line  was Great Western Railways Chief Engineer, James Inglis, and the final route he chose   reflected the shortest  distance but  with  diversions to  avoid  difficult terrain.

One  feature that  could not be  bypassed  was the valley and stream  near to Stanway, which required a 210 yard long  viaduct, incorporating  fifteen 36 ft wide  arches.  The 50ft high   structure    also needed to  incorporate a gradual   curve and a 1 in 150 slope  down from the Toddington end towards Broadway.

Work on the viaduct started in March 1903,  and the gang of  50 or so regular men began  by  excavating for the  pier  foundations  down to a depth of 12 ft.  By the Autumn,  all the blue brick piers and arches were nearing completion.  However, at 8.15am on Friday 13th (!) November, arch No 10 collapsed  without warning,  bringing down  a 14 ton steam crane  which had been used to hoist up  materials from ground level.  The noise of the collapse was heard over a mile  away.

Men  from all parts of  the line rushed to the site   and immediately   commenced      a rescue operation.   They managed to  find the  crane driver, a man named Smith, and placed him under arch No 9, while  they  tried to get another  fellow who was  under the remains of the crane.  However, arch No 9 then collapsed, burying Smith again along with four other men.    Just 40 minutes later arch No 8  fell in, with cracks appearing in arch No 7.   Smith was eventually  pulled from the debris,  but tragically   died later that night  in  the Cottage Hospital in Winchcombe.

He was one of   four  men killed,   with seven others  injured.   The death toll could well have been much worse as  the men  generally  took  their breakfast at 8.30am beneath the same arches that collapsed.  One of the injured men remained in hospital for  seven months,  so severe was the extent of his injuries, but he  must have been well looked after,  for after his discharge, he married the Matron!

The  subsequent Inquest  returned  verdicts of  ‘accidental death’,   but with a  rider     concluding that, considering the state of the weather, insufficient time had  been  allowed  for the lime mortar to set  before the supporting centres were  removed. The positioning of the crane was  also criticised.  The Coroner  also recommended that  arches of this type should be  built using cement mortar during  the winter period.

The viaduct was  eventually completed without further mishap  by the summer of 1904.  The contractor also paid compensation for the  loss of life   and  injuries.

Next month: Weston  gets its station.

 

The Railway Station – Part 5

The summer of 1904 saw a concerted effort to   open  the line from Honeybourne to Broadway.   This included completing construction of the station serving Weston, but being midway between two villages, it  was  originally named  ‘Bretforton and Weston-sub-Edge’ ( with two hyphens!):  this was   subsequently shortened to  ‘Weston-sub-Edge’  in 1907.

Weston station  had the usual 400ft long platforms,  with  a waiting shelter on  the far platform – this was accessed by way of  a footpath from the nearby road bridge that had been built to carry the Weston – Bretforton road over the new track.    The main  building  on the platform  closest to the village comprised  Station Masters office, Booking Hall, Ladies Waiting Room and Gents Toilet.    There was also a signal box, goods shed and a short siding to the  weighbridge.

Staffing extended  to   a  Station Master, Mr D G Merritt,  with  one Porter/Signalman.   There was a house  for the Station Master, and two other  dwellings  for the track maintenance team  of  ganger and platelayer.   All   shared a pump, supplemented by a churn of water sent  to each house every day  by train from Toddington. Throughout its life the station was lit by oil lamps.

Sometime during July 1904, a small fire broke out  at the station site.  A telegram  was sent to  the nearest fire brigade at Broadway, who arrived some 45 minutes later to find the  blaze all but extinguished.   This  response time was  considered  good  for the  3½ miles travelled, together with  the time taken for   the men,  all being  volunteers, to assemble  and then  catch the horses to  pull the fire engine!

This incident doesn’t appear to have  delayed  the opening of the station, as the  first  train bound for  Broadway left Honeybourne  at 07.14am on 1st August  1904.  It comprised  six all third class coaches,  but with only 15 passengers on board.  Several others    boarded at Weston, to be greeted at Broadway by a large crowd.

The service soon  increased to ten trains  a day in each direction with  freight forming a  significant  proportion of traffic.  Milk  was sent  from Weston by Tredwells, Brodys and Robinsons, together with  fruit and  vegetables  by  J Haydon.   Apples  were also  sent  by Merivale Fruit Farm and if  Webbs at Mickleton  couldn’t get  all their cauliflowers out via Long Marston, they would dispatch some from Weston to ease congestion.  Not too far from the station was the slaughter house of D Perkins, who sent meat regularly up to London in casks.  When he had enough bones, these would be sent to the Sheppy Glue Company in Kent.

Next month: What did Weston Station look like?

(Published in The messenger September 2012)

 

The Railway Station – Part 6

 

‘Picture by Jeff Wood/Kidderminster Railway Museum’

 This is  Weston Station looking back  towards  Broadway.   Taken  on 30th May 1959,  it shows 9400  class 0-6-0PT   locomotive number 9441 on the 17.55 Cheltenham St James to Honeybourne  train.

By 1959,  Weston Station  had  become an unstaffed halt.  However, the projecting canopy shows where the booking office had been  located, and the hanging sign still announces the presence  of the gents toilet!    The  waiting shelter on the  far platform is screened by the train.

The  bridge at the end of the platform    carries the Bretforton Road.    The  further bridge, visible  in the far  distance,  was built to   accommodate a track  running from Saintbury.   This structure no longer exists, having been demolished when it became unsafe, but its  very existence does illustrate the  responsibility that fell upon the constructors of the line to accommodate even minor rights of way.

In the absence of a pedestrian  bridge, passengers  were supposed to use a path  down from the road to gain access to the  far ‘Up’ platform.  As this involved a long walk back to, and  along, the road I  am told    that  most opted to  walk over the tracks by way of   the barrow crossing  located  at  the other end of the platform!

I am obliged to  David Postle  of the Kidderminster Railway Museum for  providing this picture.

Next month:  The end of the line for Weston-sub-Edge station.

(Published in The Messenger October 2012)

 

The Railway Station – Part 7

The demise of Weston Station occurred gradually.  The   post of Station Master was  abolished in 1932, when  responsibility was transferred to  Broadway.  The signal box closed  on 8th October 1950 having been  preceded by the closure of the goods yard on 2th September 1950,  at which point the station became an unstaffed halt, albeit a very large one!  The halt closed finally to passengers on 7th March 1960.

Managing to escape the ‘axe’ wielded by Dr Beeching, the line  continued to be used as a link between other  regions, but the  final nail in  its coffin seems to have been the derailment,  on 25th August 1976, of  22 wagons  on   the 06.36 coal train from Toton to Severn Tunnel Junction,   following  an embankment  landslip  north of Winchcombe  Station, at a point known locally as Chicken Curve.  It was   considered uneconomic  to repair the damage  and the   complete Cheltenham to Stratford line was  closed officially by British Rail  on 1st November 1976.

Following early  efforts  focused upon the reopening of the complete service, the Gloucestershire Warwickshire Steam Railway was formed in 1981 with the aim of  one day restoring  the line from Stratford Racecourse to Cheltenham Racecourse.  Utilising finance from shareholder capital and donations,   the track bed  from Broadway to Cheltenham Racecourse was purchased from BR.  Although  most of the buildings and all of the line had gone, by  1984 work had advanced  sufficiently   to allow  the first public train to operate over a ¼ mile  of track, and on Sunday 22nd April, Nicholas Ridley MP, Secretary   of State for Transport cut the ribbon to mark the official opening.  Since then the line has been extended to Cheltenham Racecourse  and  quite recently  to  Broadway.

As  mentioned in Part 1, the old  station site is now used by CRH Plant, who have operated   from there since 1965.  The waiting shelter  from the far platform was  taken down and  re-erected at Carrog Station on the Llangollen line. The only remaining building is the weight bridge office, with  all other  structures having  been demolished down to   ground level.

The  track bed  is now owned by Sustrans for use as a footpath and cycle track and  the nearby road bridge carrying the B4035 is propped  from track level.  Thus the chances of  the line  reaching  Honeybourne again,  let alone the    ultimate  goal of Stratford Racecourse seems highly unlikely.  But who knows?

As  mentioned at the start of this series, my prime source has been  the  excellent book by the late Audie Baker, ‘The Illustrated History  of  The Stratford onAvon to Cheltenham Railway’,  together with   various posts on the internet and information from villagers who experienced  the age of steam.

(Published in The Messenger November 2012)

 

The Railway Station –  Part 8

Loose ends

Photo: Audie Baker

I always invite comments  and was therefore   delighted to be contacted  by Jane Jordan, who pointed out that  when describing the  local stations on the  Oxford to Evesham line, I had omitted to mention the Halt at Mickleton.   This was located close to the bridge carrying the line over the road to Weston and reached by  steps  up from the road.  Opened in November 1937, it only survived until October 1941, presumably due to lack of usage.  This is not surprising, given the long walk from Mickleton  village.

Jane also   mentioned that  she was born  and grew up in a house built originally as a pub for the navvies  working on the  Mickleton tunnel.    Now known as Nineveh Bridge  House, it is located close to the railway bridge  over  Smerril Bank, that is,  the road running from Mickleton up towards Chipping Campden.

On a similar theme, Stephen Barnett also provided me with further details relating to the construction of the Honeybourne to Cheltenham line and in  particular  the  navvy camp  in Saintbury, a wooden building located  approximately half way between the  phone box and the church. After the departure of the navvies, this structure served as the village club until about 1967/8, when it was demolished  by Stephen’s uncle and grandfather, assisted by Stephen.  Some of the salvaged timbers were  then  used to build a  shed in the garden of No 6 Dovers View, before eventually  being   used for firewood.

The above photograph is included by kind permission of Helen Baker, whose late husband’s book on the  construction of the Honeybourne to Cheltenham line   has been my primary source for  this series of articles.  The picture  shows Weston station during the 1930’s   and before the fields to the left of the track were  used for the construction of   a WW2 airfield.

(Published in The Messenger December 2021)